Shortest path for new conduit is through the wall in front of the house to get to a distribution panel in the garage. Is there a way, per code, to come through the poured concrete underground then maybe 60 feet to garage? I have access inside the basement to drill hole right next to main panel on basement front wall.
Trying to avoid the visible conduit on the front of the house.
Option 2 is maybe 2x or more total the distance coming out the back of the house traditionally (about 30 feet) then a longer run underground.
In planning stages. Thinking 100 amp for now.