Hey guys!
My ductwork came in on Friday and my CVMAX was delivered yesterday. Yesterday my friend and I mounted the CVMAX. It took much longer than I was hoping. A few pieces simply didn't fit in spite of them being machined by CNC. I had to modify these components. The 90 degree filter transition being one. I can't remember the other. I think it was the opening that accepts the filter transition.
I still have to securely fasten the blower housing to the mounting brackets after I leveled it with shims. My wall is quite out of plumb.
So today I started to install the Nordfab duct work. All by myself today so I'm using a long furring strip with a V notch at the top to help bear the weight as well as to assist in leveling when fastening the branches to the wall.
You'll notice that the CVMAX is a left hand unit and I have it running from left to right as if it were a right handed unit. This is where my 220V circuit for the cyclone is. I really wanted the cyclone here. Maybe one day I'll regret it. I hope not. It's quite difficult to have to try to think of absolutely everything. I probably should've put the cyclone toward the front of the shop. Less distance to travel when emptying the bin. But I preferred to have it away from the lumber rack as I plan to build much storage and cabinets and such near the miter saw.
So here's some pics...