October 12th Update
Today, an appointment was cancelled so I had an unexpected 5 hours to work on the deck. As a result, all the beams have been installed, and most of the joists have been installed.
There were a lot of irregular angles to content with but I found that by clamping the 2x6 and 2x8 timbers to the miter gauge I could easily cut most of them.
Deck building 38 -Most of the angles I was able to cut on table saw -small.JPG
I used long spikes on some of the joints:
Deck building 39 -Some joints recieved large nails -small.JPG
Here is the end result after today’s labour:
Deck building 40 -Beams all in and joists mostly in -small.JPG