Originally Posted by
Robert Engel
I'm betting the concrete displaced 95% of the water in the footers during the pour. I'm also betting they used a stiffer mix.
When I worked for a general contractor in So. FL many years ago, it was common practice to see the block on site before the slab pour and the block layers to show up within 2 or 3 days later. They laid 1/2 walls the first day, the top 1/2 the next, then we framed for the tie beams the next day and poured the tie beam and columns the day after that.
2 days after that, we stripped the tie beam forms and started mounting trusses.
By the time the supposed 28 day cure was over the drywall was either done or going up.
Every house we've seen go up near here takes a year to finish.
“Travel is fatal to prejudice, bigotry, and narrow-mindedness..." - Mark Twain